Recently, the 5t/hr detergent powder packaging production line of Nice designed and constructed by our company has been put into operation smoothly. The project is China's first daily chemical manufacturing enterprise established in Angola, Africa. After joint efforts of various parties, it took less than 8 months from the construction to the operation, which was praised locally as 'the speed of China'.
发布时间:
2020
-
03
-
06
浏览次数:15
The foreign project, the full-automatic spray tower detergent powder production line with annual put of 50,000 tons designed and constructed by the company. In order to ensure that the project is delivered on schedule, the installation work during the Spring Festival continues on schedule.Years can fade the memory, but can not fade these silently dedication in the work of the people, thank them for their efforts.
发布时间:
2020
-
02
-
25
浏览次数:11
New Year time is here. Zhejiang Meibao Industrial Technology Co.,Ltd. hope you have a wonderful New Year. May every day hold happy hours for you.
发布时间:
2019
-
12
-
31
浏览次数:15
After one year of friendly and close cooperation between the two parties, the 80,000 tons/year of high tower detergent powder production line designed and constructed by our company has been successfully put into production in India recently. The indicators of quality, energy consumption and environment meet the design requirements and reach the internationally advanced level.
发布时间:
2019
-
12
-
16
浏览次数:17
The 30,000 tons of wet process sodium silicate production line designed and constructed by our company has produced qualified products on November 18 after three days of commissioning. It has been put into continuous production and operation.
发布时间:
2019
-
11
-
28
浏览次数:22
The 18th ICIF China in 2019 was held in Shanghai New International Expo Center from 18th, September to 20th, September. Our company participated in this exhibition and promoted the company's main products, such as detergent powder production equipment, liquid detergent production equipment, hot air furnace and other products.
发布时间:
2019
-
09
-
29
浏览次数:20
From August 11 to 17, our factory concentrated all resources and worked continuously. Under the close cooperation of technical, engineering and foreign trade departments, we loaded 60 containers of detergent powder equipment within 7 days and passed customs clearance successfully. These equipment are sent to Zambia, Angola and other countries for detergent powder project.
发布时间:
2019
-
08
-
23
浏览次数:21
On August 5th, the biomass fired hot air furnace of 12 million KCal/hour for Indonesian ceramics contracted by our company was put into operation .
发布时间:
2019
-
08
-
06
浏览次数:26
The expansion project of our factory is proceeding smoothly according to the plan since April. The functional areas such as material stacking, sheet metal manufacture processing, riveting, precision machining, assembling, commissioning, testing and finished product storage are more reasonable and tidy.This will provide the solid foundation safeguard for the production.
发布时间:
2019
-
07
-
12
浏览次数:12